CRA application timeline

Regulation (EU) 2024/2847 applies in phases. The dates below come from Article 71 (Entry into force and application).

  1. Adoption

    The Regulation is adopted by the European Parliament and the Council under the ordinary legislative procedure.

  2. Publication in the Official Journal

    Published in OJ L of 20 November 2024 as Regulation (EU) 2024/2847.

  3. Entry into force

    Per Article 71(1), the Regulation enters into force on the twentieth day following its publication. From this date, the legal text exists; most obligations are not yet directly applicable.

  4. Technical descriptions of important and critical products

    The Commission adopts Implementing Regulation (EU) 2025/2392, describing each category of important products (Annex III, classes I and II) and critical products (Annex IV). It does not change the lists; it says what falls inside each category. Article 7(4) required it by 11 December 2025.

    Article 7(4); Implementing Regulation (EU) 2025/2392.

  5. When a CSIRT may delay passing on a notification

    The Commission adopts Delegated Regulation (EU) 2026/881, setting the cybersecurity-related grounds on which the CSIRT that receives an Article 14 notification may delay disseminating it to other CSIRTs. Article 14(9) required it by 11 December 2025.

    Article 14(9); Delegated Regulation (EU) 2026/881.

  6. Chapter IV (Articles 35–51) applies

    Notification rules for conformity assessment bodies start to apply. Member States must designate notifying authorities and start to notify bodies so that, at full application, accredited conformity assessment capacity is available.

    Article 71(2), second subparagraph.

  7. Article 14 reporting obligations apply

    Manufacturers must report actively exploited vulnerabilities and severe incidents simultaneously to the CSIRT coordinator and ENISA via the single reporting platform (Article 16). Timelines: 24-hour early warning, 72-hour notification, 14-day final report for vulnerabilities; 24h/72h/1-month for severe incidents.

    Article 71(2), second subparagraph.

  8. Enough notified bodies, in principle

    Member States shall strive to ensure that the Union has a sufficient number of notified bodies to carry out conformity assessments, so that manufacturers who need a third-party assessment are not left waiting at full application.

    Article 35(2).

  9. Full application

    All remaining obligations apply. Products with digital elements placed on the Union market must comply with the essential cybersecurity requirements (Annex I), carry the CE marking, and be accompanied by an EU declaration of conformity. Penalties (Article 64) become enforceable.

    Article 71(2), first subparagraph.

  10. Older certificates stop counting

    EU type-examination certificates and approval decisions on cybersecurity requirements, issued under other Union harmonisation legislation, remain valid until this date unless they expire earlier or that legislation says otherwise.

    Article 69(1).

  11. Review of the single reporting platform

    The Commission reports to the European Parliament and the Council, after consulting ENISA and the CSIRTs network, on how well the single reporting platform works and on the use of the grounds for delaying dissemination.

    Article 70(2).

  12. First evaluation of the Regulation

    The Commission submits its first report on the evaluation and review of the Cyber Resilience Act, and one every four years after that. The reports are public.

    Article 70(1).

Products already on the market

A product placed on the market before 11 December 2027 is subject to the Regulation's requirements only if, from that date, it undergoes a substantial modification. The exception is reporting: the Article 14 obligations apply to every product in scope, including those placed on the market before 11 December 2027. A manufacturer therefore has to report actively exploited vulnerabilities and severe incidents in products it shipped years ago, from 11 September 2026.

Article 69(2) and (3). For what the reporting clock requires in practice, see CRA Article 14: the 24h/72h/14-day reporting clock.

Application by article

Article / ChapterApplies fromReference
Article 14 (reporting obligations of manufacturers)11 September 2026Article 71(2)
Chapter IV — Articles 35 to 51 (notification of conformity assessment bodies)11 June 2026Article 71(2)
All other articles, annexes, and the essential cybersecurity requirements11 December 2027Article 71(2)

The dates above are the application dates set by the Regulation itself. Where the date falls on a weekend or non-working day, EU practice still treats the stated date as the effective date — the regulation does not provide a working-day shift. Verify against the OJ before relying on a specific calendar day.